Flathead Area Mountain Bikers - Preserving and advancing mountain bike activities in the Flathead Valley
  • Home
  • About FAMB
    • Who We Are
    • FAMB Position Statements
    • Contact / Subscribe
    • Flathead Trails Association
  • Support FAMB
    • Donate
    • Join/Renew
    • Store
    • Become a Sponsor
  • Local Trails
  • Events
    • TNRL
    • Women's Skills Clinics
    • Youth Skills Clinics
    • Volunteer Trail Days
    • Register for Upcoming Events
  • Projects
    • Taylor Hellroaring
    • Crane Mountain
    • Spencer Mountain
    • Flathead Trail Crew >
      • Trail Crew Updates!
    • Past Projects >
      • Hungry Lion
      • Whitefish Range Partnership
      • Crystal Cedar
      • Tally Area Trails
      • Whitefish Mountain Resort
      • Armory Pump Track
      • The Whitefish Trail
  • Log In
  • JOIN FAMB!
  • Home
  • About FAMB
    • Who We Are
    • FAMB Position Statements
    • Contact / Subscribe
    • Flathead Trails Association
  • Support FAMB
    • Donate
    • Join/Renew
    • Store
    • Become a Sponsor
  • Local Trails
  • Events
    • TNRL
    • Women's Skills Clinics
    • Youth Skills Clinics
    • Volunteer Trail Days
    • Register for Upcoming Events
  • Projects
    • Taylor Hellroaring
    • Crane Mountain
    • Spencer Mountain
    • Flathead Trail Crew >
      • Trail Crew Updates!
    • Past Projects >
      • Hungry Lion
      • Whitefish Range Partnership
      • Crystal Cedar
      • Tally Area Trails
      • Whitefish Mountain Resort
      • Armory Pump Track
      • The Whitefish Trail
  • Log In
  • JOIN FAMB!

FTC - Trail Work Report

7/12/2024

0 Comments

 
Swan Lake Ranger District
#725 Switchback Trail: 1.3 of 2.4 miles maintained. 0.1 of 2.4 miles improved.
  • Days on trail: 4
  • Brushed from mile 1.3 to top
    • Including previous work, finished brushing entire trail.
  • Cleared trees: 2
  • Cutbacks: 3
  • Treadwork (mileage from top)
    •  1.3 - Removed rootball, cutback: 50 ft tread
    • 1.4 - Fixed damage from fallen trees, benching: 70 ft tread
    • 1.6 - Fixed outsloping due to rock: 20 ft tread
  • Future work (partner with FS Crew):
    • Intermittent sections of cupping from top to 5th switchback. 1-2 days.
0 Comments

FTC- Trail Work Report

7/5/2024

0 Comments

 
Swan Lake Ranger District
#725 Switchback Trail: 1.3 of 2.4 miles maintained.
  • Days on trail: 3
  • Brushed from bottom TH to mile 1.3.
  • Cleared down trees: 12
0 Comments

FTC - Trail Work Report

6/28/2024

0 Comments

 
Tally Lake Ranger District
#800 Bill Cr: 0.3 of 3.9 miles improved
  • Days on trail: 4
  • De-cupped miles 1.1-1.3 from Reid intersection.
    • Total: 1,310 ft
0 Comments

FTC _ Trail Work Report

6/21/2024

0 Comments

 
Tally Lake Ranger District
  •  #800 Bill Cr: 0.3 of 3.9 miles improved
    •  Days on trail: 3
    • De-cupped miles 1.0-1.2 from top (Reid intersection).
      • Total: 820 ft
    •  Improved ravine section 0.6 miles from top.
      • Total: 150 ft
      • Widened tread, flattened cupping, added drains.

Swan Lake Ranger District
  •  #104 Blacktail to Lakeside: 3.4 of 3.4 miles maintained
  •  Days on trail: 1
  •  Teamed up with Swan Lake Trail Crew to address problems on trail.
  •  Trail has been cleared and drains installed.
  • We have reports that Foys to Blacktail is clear and in good shape.
0 Comments

FTC - Trail Work Report

6/14/2024

0 Comments

 
​Details
● #800 Bill Cr: 0.3 of 3.9 miles improved
○ Days on trail: 2
○ De-cupped miles 0.7-0.9 from Reid intersection.
■ Total: 590 ft

● Spencer Mtn: 2 of 10 trails maintained
○ Days on trail: 1
○ Malice in Plunderland
■ Removed dangerous leaner by the Sushi Roll
○ Upper Maple Syrup
■ Removed leaner at midway point (flat rooty section)
■ Brushed entire length of trail (0.7 miles from summit to helipad)
0 Comments

FTC - Trail Work Report

6/7/2024

0 Comments

 
Details
  • #210 Lupine Lake: 1.3 of 3.9 miles maintained
    • Cleaned and installed drains from trailhead to lake. With work from last week, entire trail has been drained.
    • Obstructing trees removed: 2

  • #287 Pine Grass: 2.7 of 6.2 miles of trail maintained
    • Partnered with FS and MCC on 6/6/24 for de-curbing near top of Ashley Mtn.
      • Total between 7 personnel: 450 ft.
    • Installed drains along lower section from 210 Lupine Lk to gravel pit parking lot.
    • Obstructing trees removed: 5
    • Cutbacks performed: 1

  • Prospective work: Install turnpike from mile 0.2-0.5 north of parking area.

  • Spencer: 3 of 10 trails maintained
    • Maple Syrup
      • Cut out reported tree near top.
    • Big Gulps, Eh?
      • Polished new reroute in bottom section.
      • 5 cutbacks in bottom section to widen trail corridor and remove obstacles.
    • Malice in Plunderland
      • Re-built and polished final table below drop park.
        • Lip is sharp, jump is longer to match speed from biggest drop.
0 Comments

FTC - Trail Work Report

5/31/2024

0 Comments

 
​Details
  • #800 Ashley Mountain: 1.9 of 4.3 miles of trail maintained
    • Cleaned and installed drains along entirety of trail. With last weeks work, trail is clear and drained.
    • Obstructing trees removed: 10

  • Prospective work:
    • Deep trenching at mile 1.6-1.8 from summit.
    • 3 leaners at mile 3.5 from summit. Trail is passable, but they will most likely come down this summer or winter.


  • #310 Ashley Mountain: 5.5 of 5.5 miles of trail maintained
    • Cleaned and installed drains along entirety of trail.
    • Obstructing trees removed: 4
    • Cutbacks performed: 4
    • Leaners removed: 4
    • Spot brushed to improve sightlines and maintain trail corridor.


  • #210 Lupine Lake: 1.3 of 3.9 miles maintained
    • Cleaned and installed drains from lake to summit.
    • Obstructing trees removed: 3
    • Leaners removed: 2
0 Comments

FTC - Trail Work Report

5/24/2024

0 Comments

 
Details
  • #800 Bill Cr: 5.1 of 5.1 miles of trail maintained
    • Cleaned and installed drains along entirety of trail
    • Obstructing trees removed: 7
    • Spot brushed totaling .2 miles. Mostly through patches of Snowbrush/Ceanothus and at road xings.
    • Tread work done at miles .6 and 1.0 from top.
      • Widened big right turn on inside to keep outside as berm for wheeled vehicles, and a flat bottom for hikers/uphill wheeled vehicles.
      • De-curbed trail just above road xing for ~60 ft.
  • #800 Ashley Mountain: 2.4 of 4.3 miles of trail maintained
    • Cleaned and installed drains along entirety of trail.
    • Obstructing trees removed: 1
      • Road 313 obstructing trees removed: 3
    • Tread work at mile 2.5 from top (top of troad section)
    • Trail crossing upslope drain for road was removed and replaced with rocks to allow for drainage and provide a trail surface.
0 Comments

FTC - Trail Work Report

5/10/2024

0 Comments

 
​Details
  • #800 Reid Divide: 3.9 of 9.9 miles of trail maintained
    • Cleaned and installed drains from Tally Lake CG Trailhead to Boney Gulch intersection
    • Obstructing trees removed: 1
  • #801 Boney Gulch: 2.6 of 2.6 miles of trail maintained
    • Cleaned and installed drains along entire trail.
    • Obstructing trees removed: 3
    • Cutbacks: 1
0 Comments

New Facebook Group

4/12/2024

0 Comments

 
I have a created a new Facebook group I hope you will check out, note this is not a FAMB specific page so invite anyone that would be interested to join!

This is a Flathead Valley community forum for posting trail conditions, finding a riding partner, bike related events, discussing mountain bikes, parts and gear, as well as looking for advice and asking questions! If you are an avid mountain biker in the Flathead, have just moved here, or are new to mountain bikes and are looking for tips you are in the right place.

https://www.facebook.com/groups/925664545902007/
0 Comments
<<Previous
Forward>>

    About Us

    Flathead Area Mountain Bikers, a 501(c)(3) nonprofit, is working to promote mountain biking and improve trail access in the Flathead Valley.

    Archives

    June 2025
    May 2025
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    December 2023
    August 2023
    July 2023
    June 2023
    May 2023
    January 2023
    October 2022
    July 2022
    June 2022
    April 2022
    March 2022
    February 2022
    September 2021
    July 2021
    May 2021
    March 2021
    February 2021
    October 2020
    August 2020
    July 2020
    March 2020
    December 2019
    September 2019
    July 2019
    May 2019
    November 2018
    August 2018
    June 2018
    May 2018
    February 2018
    January 2018
    August 2017
    July 2017
    April 2017
    February 2017
    October 2016
    September 2016

    Categories

    All

    RSS Feed

Picture

 Preserving and advancing mountain bike activities in the Flathead Valley.

Donate
Join/Renew
Contact
© 2022 Flathead Area Mountain Bikers | All Rights Reserved